Foster School Building Project – Passed on November 8th, 2022
After an almost unanimous vote at the November 1st Special Town Meeting, the project was placed on the ballot for the November 8th election. At the ballot box, 72% of residents voted in favor of the project far surpassing the needed threshold of 51%.
Thank you, Hingham, for your overwhelming support for this project at both Special Town Meeting and at the ballot box!
Currently, the Foster School Building Committee as established at the 2017 Hingham Town Meeting, is responsible for the oversight, design, and construction of the Foster School Building Project.
Updates – School Building Project
November 30, 2022
The School Building Committee awarded the bid to K. R. Rezendes Inc (KRR) last week for the first phase of work at the Foster School for the construction of the new elementary school building.
The contractor began immediately developing the Storm Water Protection Plan which will then trigger the review by the Conservation Commission and Planning Board. This review is expected to take two weeks. Once complete, the site work will begin for Phase 1. We look forward to providing updates on the project throughout the year.
December 23, 2022
There will be a temporary parking lot established at the front of the building to make room for the access road being developed.
January 2, 2023
The temporary parking lot is complete.
The temporary playground is close to completion.
The new access road is complete.
Learn more about the project using the resources below:
Educational Video Series
- Deficiencies of the Current Foster School
- Benefits of the New Foster Design
- Foster’s Gym Size
- Daily Maintenance at Foster School
- Challenges of Small Group Spaces
Learn About the Deficiencies of the Current Foster School
Learn About the Benefits of the New Foster Design
Foster’s Gym Size
Daily Maintenance at Foster School
Challenges of Small Group Spaces
- Foster’s Multipurpose Room
- Temperature Control at Foster
- Boiler Room at Foster
- Foster Classroom Access Challenges
Foster’s Multipurpose Room
Temperature Control at Foster
Boiler Room at Foster
Foster Classroom Access Challenges
About the School and Project: